M&S, Marble Arch

Following a successfully negotiated bid we secured the contract for the remodel and modernisation works within M&S’s flagship store. The works were untaken on nights over a 6 month period which saw the introduction of a number of new cafes and catering offers with works spread over 7 floors.

.

Services included:

  • Kitchen extract ventilation & stainless steel canopies to five catering concessions
  • M&S Bank fit out
  • Replacement of 2No roof top chillers totalling 1300kw
  • Chiller refurbishment
  • LTHW heating & boiler plant installation serving dedicated foodhall heating
  • Strip out of existing services
  • Fire rated ductwork
  • Hot & Cold water services to Deli, Cafes, Bakery, Hot food on the move concessions and main distribution supplies over 7 floors
  • Above ground drainage, Grease Interceptors & Enzyme Dosing, condense drainage
  • Installation of 26No pumped drain units
  • Gas pipework
  • BMS controls
  •