M&S, Marble Arch
Following a successfully negotiated bid we secured the contract for the remodel and modernisation works within M&S’s flagship store. The works were untaken on nights over a 6 month period which saw the introduction of a number of new cafes and catering offers with works spread over 7 floors.
.
Services included:
-
Kitchen extract ventilation & stainless steel canopies to five catering concessions
-
M&S Bank fit out
-
Replacement of 2No roof top chillers totalling 1300kw
-
Chiller refurbishment
-
LTHW heating & boiler plant installation serving dedicated foodhall heating
-
Strip out of existing services
-
Fire rated ductwork
-
Hot & Cold water services to Deli, Cafes, Bakery, Hot food on the move concessions and main distribution supplies over 7 floors
-
Above ground drainage, Grease Interceptors & Enzyme Dosing, condense drainage
-
Installation of 26No pumped drain units
-
Gas pipework
-
BMS controls